After 5 times shocks and the quick cut tests between 220kV and 132kV, the inversely feeding for Unit 4 of Chashma Nuclear Power Plant was successfully completed on 23th, March, 2016.
The implementation of the feeding guarantees the quality of the spplied power and provides the solid condition for the following hydrostatic test.